Construction management of the onshore part of the "Windplanblauw" wind farm
In addition to the nearshore part, Aratis is also responsible for construction management for the realisation of the onshore part of Windplanblauw.
On behalf of the client Molenrak (consisting of Vattenfall and SwifterwinT), Aratis is responsible for the integrated construction management of the Balance of Plant, Wind Turbines and Transport & Installation contracts. For this construction management of the 24-turbine wind farm, Aratis is supported, as with the onshore part of Windplanblauw, by its partners Halsten, Aryo System, Windunie, Arcadis, Windbase, Topwind, IX Wind, WSP and ENSOL.
Wind Plan Blue Scope of the assets of the onshore section
Windturbines
37 Vestas Enventus V 162-5.6 MW wind turbines with a tip height of 249 m for the onshore section (equivalent to the electricity consumption of 270,000 households)
Balance of Plant
Balance of plant for the 37 wind turbines: 37 foundations with a diameter of 22 m with a total of 1,300 vibro piles
GDS Substation
150 KV Substation GDS – Export cable 6 km – Connection to the Tennet station
Integrated Construction Management
Aratis works with its partners and the executing market parties according to the IPM model, making full use of the Aratis Project Information Management System (PIMS) within the project organisation. Through this integrated approach, Aratis fulfils the clients' wish to manage the park sections as a whole. This integrated approach also means that stakeholder management and communication are centrally organised.